The much-delayed programme to bring two new Air Force One aircraft online is facing further setbacks as a catalogue of ongoing issues continues to plague the process to prepare the aircraft for presidential service.
According to a new report released by the US Government on 3 August (prepared as part of the Pentagon’s fiscal 2027 budget submission), the programme is suffering from various complications that will delay the delivery of the two converted Boeing 747-8 aircraft, known in US military nomenclature as the VC-25B, until 2028
The issues include the primary communications system (which requires replacing), interior design problems, electrical wiring issues, structural defects, and preparations for flight testing, all of which will need resolving before the aircraft can be handed over to the US Air Force (USAF). “The design maturity for the aircraft interior continues to lag due to numerous technical and certification issues,” the report stated
Communications system will be obsolete by 2028
Asthe US Government report said that a secret communications system which has already been installed in the two new VC-25B aircraft will pose a security threat before the delivery of the aircraft in 2028. Iit will cost tens of millions of dollars to replace the system so that the aircraft are fit-for-purpose as the primary presidential transport aircraft
“The current Mission Communication System (MCS) baseline is not said the USAF in an update issued in April and recently declassified
“Unmitigated risk will drive an inability for Authority to Connect and Operate on vital National Security Systems required for Presidential communications,” the report added

According to the authorities, removing and replacing the MCS system will cost an estimated $73.3 million, only half of which has been allocated and approved in the current USAF appropriation budget
The revelation marks a major setback for a programme that is already many years behind schedule
Cockpit and cabin windows are also an issue
Among the other issues currently delaying the VC-25B programme are supply chain issues linked to cabin and flight deck windows for the aircraft. The report indicated that the current window contractor (GKN) is having difficulty manufacturing the cabin windows to the USAF specifications. Any further delays could delay pressurisation tests, interior installation and ground and flight testing even further
“Challenging defect criteria have been established which require defect-free sub-components, clean room facilities, and detailed processes to reduce and eliminate particles in the assembly of the windows,” the report says
There are also issues with the cockpit windshields, according to the report. The original contractor for these components ceased trading, and the replacement contractor assigned to take over the contract (PPG) has not yet received design certification
According to the report, there are no spare commercial 747-8 windshields available, and so PPG is having to develop a replacement that is suitable for use on the VC-25B
The cabin interior continues to be delayed
Another major issue affecting the progress on the two aircraft is the design and supply of the aircraft’s bespoke presidential interior. Having already replaced the original contractor (GDC Technics) for this task in 2021, this move already pushed back the delivery of the aircraft until 2028 – four years behind schedule and around the time when President Donald Trump is due to leave office.
The delays to the cabin interior (also being experienced by commercial carriers such as Lufthansaand Air India) have impacted the installation of various other linked systems, including electrical wiring and other structural modifications
This has resulted in “inefficient engineering work” and repeated changes to parts of the aircraft that Boeing had already begun modifying, delaying the programme even further

Additionally, repairs are still needed to cracks found in structural stringers on both aircraft. Stringers run along the fuselage and help the fuselage bear structural loads imposed by flight. As of the date of the report, 95 repairs or installations remained on the first aircraft and 142 on the second
The first aircraft to be delivered by 2028?
According to the USAF, despite these ongoing issues, it is continuing to work toward delivery of the first aircraft in 2028 and the second in 2029. However, the report indicated that the planned schedule will be difficult to maintain should more unexpected work emerge, or aircraft testing takes longer than expected
In July 2026, Boeing stated that it had recorded a further $280 million loss on the programme during the second quarter, after adding production and certification re
Additionally, Boeing announced that it had agreed with the USAF to transfer the aircraft from FAA certification to the equivalent military certification process, as the planemaker looks to reduce risks during the certification and flight testing processes

In the meantime, the USAF said that it remains committed to keeping the two 30-year-old VC-25A aircraft that now fill the ‘Air Force One’ role “available and mission-ready until the VC-25B can support full mission requirements.”
Notably, the report made no mention of the 10-year-old 747-8 Boeing Business Jet gifted to the Air Force by the Qatari Royal Family. Having been formally rolled out and handed over to the USAF in July ahead of the USA250 celebrations, the aircraft is now back in Texasto have apparent security gaps addressed by defence contractor L3Harris
These security issues came to light when the aircraft was supposed to take President Trump from Turkey to Washington after the NATO Summit in July. The US Secret Service insisted Trump use an older VC-25A as far as the UK due to a heightened security threat in Turkish airspace. The president later switched to a C-32A for the flight to the UK, as reported by the BBC
The president then made an aircraft switch to the former Qatari jet at an airbase (RAF Mildenhall) in the UK before continuing his journey to Washington. The exact nature of the additional work required has not been made public
Read more defence news on AGNRead more defence news on AGN
News
DefenceAir Force OneBBJ 747-8Boeing VC-25ABoeing VC-25BPresident TrumpUSAF
Sign up for our newsletter and get our latest content in your
inbox.
1
US Navy to nearly double TACAMO ‘Doomsday plane’ fleet with E-130J Phoenix II
US Navy to nearly double TACAMO ‘Doomsday plane’ fleet with…
Lockheed Martin E-130J …
August 11, 2026
2
Swarm Aero targets MQ-9 Reaper successor with mass-produced Group 5 drone
Swarm Aero targets MQ-9 Reaper successor with mass-produced Group 5…
Swarm Aero
August 11, 2026
3
Why the Red Arrows can’t simply fly home from Canada
Why the Red Arrows can’t simply fly home from Canada
Red Arrows
August 10, 2026
4
Damaged C-17 flies again after US Air Force robot makes part nobody else could
Damaged C-17 flies again after US Air Force robot makes…
C-17 Globemaster
August 10, 2026
Related Topics
More from
From an 80-mile hop to a 19-hour marathon: The Airbus A350’s shortest and longest flights
From an 80-mile hop to a 19-hour marathon: The Airbus A350’s shortest and longest flights
August 11, 2026
Archer vs Joby: Which eVTOL air taxi company is ahead in 2026?
Archer vs Joby: Which eVTOL air taxi company is ahead in 2026?
August 11, 2026
How pilots fly during a total solar eclipse
How pilots fly during a total solar eclipse
August 11, 2026
Vertical Aerospace secures $100m financing commitments to advance Valo towards certification
Vertical Aerospace secures $100m financing commitments to advance Valo towards certification
August 11, 2026
Archer’s ZEE AI predicts aircraft movements minutes before they happen
Archer’s ZEE AI predicts aircraft movements minutes before they happen
August 11, 2026
Archer vs Joby: Which eVTOL air taxi company is ahead in 2026?Archer vs Joby: Which eVTOL air taxi company is ahead in 2026?
August 11, 2026
Swarm Aero targets MQ-9 Reaper successor with mass-produced Group 5 droneSwarm Aero targets MQ-9 Reaper successor with mass-produced Group 5 drone
August 11, 2026
Vertical Aerospace secures $100m financing commitments to advance Valo towards certificationVertical Aerospace secures $100m financing commitments to advance Valo towards certification
August 11, 2026
Swarm Aero targets MQ-9 Reaper successor with mass-produced Group 5 droneSwarm Aero targets MQ-9 Reaper successor with mass-produced Group 5 drone
August 11, 2026
Archer to acquire Wisk, Insitu and SkyGrid as Boeing takes 19.75% stakeArcher to acquire Wisk, Insitu and SkyGrid as Boeing takes 19.75% stake
August 10, 2026
US Air Force says B-21 Raider remains on track for 2027 service entry
US Air Force says B-21 Raider remains on track for 2027 service entry
August 10, 2026
Ukraine moves towards anti-ballistic missile capabilities as Freyja takes shapeUkraine moves towards anti-ballistic missile capabilities as Freyja takes shape
August 7, 2026
Vertical Aerospace secures $100m financing commitments to advance Valo towards certificationVertical Aerospace secures $100m financing commitments to advance Valo towards certification
August 11, 2026
eSAF could solve aviation’s fuel problem. So why is almost nobody making it?
eSAF could solve aviation’s fuel problem. So why is almost nobody making it?
August 7, 2026
Why is sustainable aviation fuel so scarce and expensive?Why is sustainable aviation fuel so scarce and expensive?
August 1, 2026
Amsterdam Schiphol champions airport quality as it reveals €801 million investment
Amsterdam Schiphol champions airport quality as it reveals €801 million investment
July 29, 2026